Southeastern services will be running over the Christmas and New Year period, but timetable changes and engineering work may affect journeys. Please plan ahead and check before travelling.
The Christmas period sees a significant reduction in London-bound commuters (travellers who exit London terminals before 10am). With fewer passengers over the festive period, an adjusted timetable will run on weekdays from Monday 21 December. Services on Christmas Eve shut down by approximately 10pm, while no services run on Christmas Day and Boxing Day.
Southeastern are running additional services out of central London until approximately 2:30am on New Year’s Day. When service resumes later that morning, a Sunday service will be in operation. Normal services will resume on Monday 4 January, when the network traditionally sees a return to regular commuting levels.
From 25–28 December, no services will run from London Charing Cross, Waterloo East or London Cannon Street for essential signalling upgrades in the Lewisham area. A limited service will run to and from London Bridge, with other services diverted to and from London Victoria.
These lines will close again after the last extra train has completed its journey following the New Year’s Eve celebrations, fully reopening for the start of services on Monday 4 January 2027.
What work is being carried out?
During the first closure, South Eastern Railway’s engineering teams will complete the £90m Lewisham signalling upgrade, activating new trackside equipment and train-control systems. At Christmas, the teams will install two signalling structures to keep drivers’ views of signals clear, connect the railway’s power supply, then clear sites and remove equipment. Over two years, more than 200km of signalling has been installed, telecoms and power cables, four new signals and 10 new equipment-case suites to connect to signalling equipment. During the second closure, the team will make adjustments and remove redundant railway equipment.
The new signalling will improve reliability and resilience across south east London and into Kent, reducing faults and delays. In recent years, failures involving the types of equipment being replaced, including track circuits, relay-based interlocking and associated lineside cabling, have caused many thousands of minutes of delay.
Simpler maintenance and fault-finding will help engineers resolve problems. Layout changes will enable higher train speeds on affected sections, while upgraded automatic route-setting will improve service management. The main benefits are fewer infrastructure-related delays and a more reliable, resilient signalling system that is easier to maintain and support in the long term.
This work forms part of a wider signalling upgrade across south London with upgrades to the signalling at Herne Hill, Nunhead and Battersea areas continuing into next year. Work to complete this significant signalling upgrade on the network will take place in the 2027 Christmas period.
Scott Brightwell, South Eastern Railway’s Director of Safety and Performance, said:
“We’re committed to keeping customers moving over the festive season, but ask them to plan ahead to avoid surprises at the station.
“Engineers will work throughout the period, including Christmas Day, Boxing Day and New Year’s Day, to deliver vital signalling improvements at a key junction on our railway.
“The upgrade will make services through Lewisham more resilient, reducing delays caused by signalling faults in south London in 2027.”
Summary of services during the 2026 Christmas period
|
DAY |
SERVICE OPERATING |
|
|
Monday 21 to Wednesday 23 December 2026 |
An adjusted service level will operate, with some additional services at the busiest times. |
|
|
Christmas Eve Thursday 24 December 2026 |
An adjusted service level will operate, with some additional services at the busiest times. No passenger trains will operate after approx. 22:00 |
|
|
Christmas Day Friday 25 December 2026 |
No Southeastern services will operate. |
|
|
Boxing Day Saturday 26 December 2026 |
No Southeastern services will operate. |
|
|
Sunday 27 December 2026 |
A normal Sunday service level will operate with some additional trains at the busiest times. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Bexleyheath / Sidcup / Grove Park / Hayes. |
|
|
Bank Holiday Monday 28 December 2026 |
A Saturday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Bexleyheath / Sidcup / Grove Park / Hayes. |
|
|
Tuesday 29 and Wednesday 30 December 2026 |
An adjusted service level will operate, with some additional services at the busiest times. |
|
|
New Year’s Eve Thursday 31 December 2026 |
An adjusted service level will operate, with some additional services. Additional early morning services from Midnight for Central London revellers. |
|
|
New Year’s Day Friday 1 January 2027 |
A Sunday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Sidcup / Petts Wood, Gillingham to Faversham / Sheerness, Otford to Ashford. |
|
|
Saturday 2 January 2027 |
A normal Saturday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Sidcup / Petts Wood, Headcorn to Ashford, Sittingbourne to Herne Bay / Dover. |
|
|
Sunday 3 January 2027 |
A normal Sunday service level will operate. Engineering work will take place on the following routes: Charing Cross / Cannon Street to Sidcup / Petts Wood, Headcorn to Ashford, Sittingbourne to Herne Bay / Dover. |
|
|
Monday 4 January 2027 |
Normal services resume |
|